First 3.2 MW Pump of Goreh-Jask Project Delivered

TEHRAN (NIOC) _ The first 3.2-MW pump made in Iran, after successfully passing performance tests, was delivered to the Goreh-Jask crude oil transfer project and reached the installation site in Pumping House No. 2, located 50 km off Bushehr.


According to the Petroleum Engineering and Development Company (PEDEC), Ali Jafarzadeh, the deputy director of the Goreh-Jask crude oil transfer project, said: "This is the first 3.2 MW pump made in Iran, following the signature of contracts for the construction of 50 pumps required for the project.”

He stated that the pump was transported to Pumping House No. 2 and installation and commissioning activities are on the agenda
.


The pumping house will be launched with 4 pumps
.

 